Beach Energy Limited (ASX:BPT) ( BEPTF) announces weekly drilling report for the week ending 23 June 2010. Highlights of the week's activities include:
Beach Operated Shale Gas Exploration - PEL 218, Cooper Basin
Drilling of a two well exploration program targeting Shale Gas potential within the South Australian portion of the Nappamerri Trough, is now expected to commence in mid to late August with Encounter-1. Weather conditions in Thailand have hindered completion of maintenance work on some of the Ensign 16 rig components and their subsequent shipment to Australia, causing the delay.
Holdfast-1, earlier planned to spud in mid July as the first well in the program, will now follow Encounter-1 due to ease of access following Cooper Basin flooding (Beach - Operator, 90%, Adelaide Energy (ASX:ADE) 10%).
Cooper/Eromanga Oil Development - Santos (ASX:STO) Operated
The Inca-1 oil exploration well (Beach 30%) is drilling ahead at a depth of 1,766 metres in the Hutton Sandstone. The well is being control drilled to an estimated total depth of 1,870 metres.
Non-operated Oil Appraisal, South Antelope Prospect, Williston Basin - U.S.A.
The Henderson 4-25H oil appraisal well is at a depth of 4341 metres (MD), drilling horizontal section in the target Three Forks Formation towards a prognosed TD of 4872m MD. Casing was installed at 3410 metres MD prior to commencing horizontal drilling. Wellsite shows within the Three Forks Formation are encouraging (Beach [USA] Inc 23.15% contributing interest).
Beach Energy Limited Change to Frequency of Drilling Reporting to ASX
Beach now intends reporting on its routine drilling activities on a monthly rather than a weekly basis, with future reports being made during the first week of each month. To meet its Listing Rule obligations, Beach will continue to make immediate disclosure to ASX of material issues, as required.
( * ) Operator
(s) Secondary Targets
BPT Beach Energy Ltd
STO Santos Limited
BPT (1) Beach Energy U.S.A Inc.
SEA Sundace
Helis Helis Oil & Gas Company L.LC
ORG Origin Energy Resources Ltd
1.
--------------------------------------
Well Participants
--------------------------------------
Coonatie-16 BPT 17.14%
PPL 131 STO* 72.32%
Gas Development ORG 10.54%
C/E Basin, SA
--------------------------------------
--------------------------------------------------------------
Weekly Progress & Summary Primary Targets
--------------------------------------------------------------
Report Time: 0600 hrs (CST) 23/06/2010 Callawonga, Toolachee,
Depth: 2524.0m Epsilon, Patchawarra
Operation: Drilling ahead in the Tirrawarra
Nappamerri Group.
Progress: 1394.0m
--------------------------------------------------------------
2.
--------------------------------------
Well Participants
--------------------------------------
Coonatie-17 BPT 17.14%
PPL 131 STO* 72.32%
Gas Development ORG 10.54%
C/E Basin, SA
--------------------------------------
--------------------------------------------------------------
Weekly Progress & Summary Primary Targets
--------------------------------------------------------------
Report Time: 0600 hrs (CST) 23/06/2010 Callawonga, Toolachee,
Depth: 3105.0m (TD) Epsilon, Patchawarra
Operation: Well is being cased and Tirrawarra
suspended as a future
multi-interval Permian
gas producer.
Progress: 0m
--------------------------------------------------------------
3.
--------------------------------------
Well Participants
--------------------------------------
Inca-1 BPT 30.00%
ATP259P STO* 70.00%
Oil NFE
C/E Basin, QLD
--------------------------------------
----------------------------------------------------------------
Weekly Progress & Summary Primary Targets
----------------------------------------------------------------
Report Time: 0600 hrs (CST) 23/06/2010 Mid-Namur Sandstone
Depth: 1766.0m Birkhead Fm / Hutton Sst
Operation: Drilling ahead in the
Hutton Sandstone.
Progress: 1677.0m
----------------------------------------------------------------
4.
-------------------------------------------------------
Well Participants
-------------------------------------------------------
Henderson 4-25H BPT (1) 23.15%
Williston Basin, North SEA 24.02%
Dakota, USA Helis* plus 7 others 52.83%
Oil Appraisal
-------------------------------------------------------
---------------------------------------------------------------
Weekly Progress & Summary Primary Targets
---------------------------------------------------------------
Report Time: 0600 hrs (local) 22/06/2010 Three Forks Formation
Depth: 4341.0m MD Bakken Formation
Operation: Drilling lateral section in
Three Forks Formation.
Progress: 2551.0m
---------------------------------------------------------------
For the complete Beach Energy announcement including Well Location Map, please view the following link:
http://www.abnnewswire.net/media/en/docs/63156-ASX-BPT-178558.pdf
About Beach Energy Limited:
Beach Energy Limited (ASX: BPT) is a long established oil and gas Exploration and Production Company. Based in Adelaide, South Australia, the Company has oil and gas reserves of 66 million barrels of oil equivalent (at 30 June 2009), an annual production in the 2008/09 Financial Year of 9.6 million barrels of oil equivalent and an active exploration program within a balanced global portfolio of tenements.
Contact:
Hector Gordon
Chief Executive Officer
TEL: +61-8-8338-2833
FAX: +61-8-8338-2336
www.beachenergy.com.au
Source:
Beach Energy Limited
Copyright (C) 2010 ABN Newswire. All rights reserved.